End of Building works.
My solicitor has advised my property is completed and ready for the final payment, so I must be quick, should I make sure the End Of Building Works has been granted before I pay the final amount, I am told the LFO is in place.
I am grateful for your help.
Thank You
-
Dear Sir/Madam,
The Certificate of End of Construction (CEC) has already been granted, don't worry.
As per our FAQ on First Occupancy Licences (LFO) and bank guarantees a developer may only request a LFO from the town hall if he already has the CEC:
Upon the granting of the Certificate of End of Construction (CEC) for a new built property, the developer may apply for a First Occupancy Licence (AKA as “Cédula de Habitabilidad” in some parts of Spain).
The CEC is a prerequisite to obtain a LFO. No CEC, no LFO.
Last edited by Lawbird Lawyer; 01-30-2009 at 10:33 AM.
-
Thank you for your prompt reply, I am very grateful for your help.
-